Seqwater creek & pipe protection works

Client

Seqwater

Project value

<$1M

Completion

September 2021

Location

Sunnybank, Qld

Sector

WATER

Following severe erosion starting with 2011 floods, erosion has exposed the Rocklea to Kuraby DN1200 water main at Sunnybank. Further erosion poses a risk of collapse of the water main into the adjoining Stable Swamp Creek. The Project required construction of a new 5.5 high gabion wall to protect the water main and reduce the risk on any future erosion.

The objective of this project is to reduce the risk of continued erosion and/or undermining, leading to failure of the water main, and subsequent disruption to water supply, along the Rocklea to Kuraby DN1200 water main at 258 Beenleigh Rd, Sunnybank.

Seqwater required a principal contractor for the installation of creek and pipe protections to mitigate further erosion, and provide a support to the exposed section of pipe, through implementing the below:

  • Support the main throughout construction of the permanent works
  • Ensure no run-off of impact upon Stable Swamp Creek.
  • Re-profile batter to achieve sound foundation and placement of gabion baskets, terraced from creek, up to and around the exposed water main.
  • Stabilise the remainder of the bank with armor rock
  • Revegetate the area and restore the natural watercourse.

What we delivered

This objective was achieved by re-profiling the creek bank to achieve a sound foundation and placing gabion baskets terraced up from the creek to prevent future erosion. Before these works commenced, the DN1200 water main was supported to ensure it is stable and prevent any movement during the construction period. Bellwether also engaged an RPEQ to design, inspect and certify the support system for the water main.

The system involved the installation of ground anchors which stabilized the bank and supported the main during construction.  This system involved no permanent attachment to main and did not damage the coating to the pipe. Furthermore, this system also provided a safe, stable bank for our crews to work under whilst installing the permanent footings and gabions.

Key outcomes

Bellwether ensured the integrity of the water main through a two-fold process. Firstly, we engaged an RPEQ to design, inspect and certify a support system for the main. Bellwether also allowed for a qualified surveyor to monitor the main so that in the unlikely event that the main did move, we could halt construction immediately.  This secondary measure provides certainty that the water network remained operational throughout construction.

Other key concerns involved with the delivery of these works include ensuring zero harm to workers and minimizing environmental impacts. We achieved zero harm to workers by implementing Seqwater’s lifesaving controls alongside Bellwether’s own ISO accredited safety system to assess and mitigate the risks during construction.

Carmichael Coal Mine & Rail Network
DTMR Henri Roberts Drive (in progress)
Blythe River Bridge Strengthening
North Brisbane Bikeway – Chalk Street to Price Street
Captain Cook Highway Smithfield Bypass
Tinaroo Falls Dam Raising
Nullinga Dam Detailed Business Case
Stony Creek & Lindenow Options
Warrego Highway / Mt Crosby Road Interchange Upgrade
Fairbairn Dam
Maturing the Infrastructure Pipeline Program (MIPP)
Land Street Bikeway Underpass Duplication
Morayfield Indoor Sports and Events Centre Expansion
Torbanlea – Pialba Road Floodway Replacements Business Case
Samford Road Options Analysis
Logan Motorway East Bound Drainage Improvements and Pavement Rehabilitation
Gold Coast Tourism Hub Project – Bundall Road Site
Greenbank Transport Corridor
South Burnett Regional Council Systems Review
Cannon Hill Shopping Centre Bus Facility – Bus Station Upgrade
Newell Highway Flood Immunity West Wyalong to Forbes
Mareeba-Dimbulah Road Widening and Roadside Safety Improvements
Calliope River Bridge and Anabranch Bridge: Engineering Analysis and Options Analysis
North Pine Hub Strategic Assessment
Gregory Highway 27B – LN1 Culverts Upgrade Planning (Business Case)
Barwon Heads Road, Black Rock Road and Staceys Road Roundabout
Pacific Highway Upgrade – Woolgoolga to Ballina
Easing Sydney’s Congestion – Pinch Point Program
Burdekin Falls Dam Improvement and Raising
M6 Early Works Construction
Warragamba Dam Expert Witness Report
South Batemans Bay Link Road
Gunns Gully Road Interchange
M1 Princes Motorway Improvements
Circular Quay Precinct Renewal
Wynnum Road Corridor Upgrade
Arrow Energy Dalby – Laydown Yard
MSC Charleville Industrial Estate
BSC Leans Creek Bridge & Richardsons Bridge Repairs
CHRC Springsure Landfill Rehabilitation
CHRC Capella Landfill Rehab & Transfer Station
MRC Whittle Street Drainage Upgrade
TRC South Street & Burton Street Intersection
Seqwater creek & pipe protection works
MRC Warland Street Drainage
MRC Mackay Bus Stop DDA Compliance Program
MRC Juliet Street Pavement Rehabilitation
NDRRA Flood Betterment Works
Retail First Brookside Shopping Centre Embankment Stabilisation & Car park extension
NSC Black Mountain Road Safety Improvements
TRC Toowoomba Waste Transfer Facilities (*3)
Australian Department of Defence – Kokoda Barracks
Australian Department of Defence – Enoggera Barracks
MRC Caping Road Bridge
DTMR Virginia Park ‘n’ Ride Upgrade
BRC Bruce HWY Upgrade & Streetscape, Gin Gin
MRC Milton Street & Archibald Street Intersection Upgrade
WDRC Warrego Highway Upgrade and Streetscape, Miles QLD
MBRC Aurthur Drewett Drive
WDRC Bundi Creek Bridge (in progress)
NSC Noosa Parade Upgrade